4th draw

Received an email from George Mason Mortgage, LLC, which informed us that they will release $71,020 to NDI.

“We received a draw request from your builder around the holidays.  The inspector finally completed the report and sent us a copy.  Photos evidence completion of drywall, trim and cabinets.  That said, we will release $71,020.00 to NDI today.”

Cabinet walk

Cabinet walk is today.  Jin and Vince met in the new house.  Dawn sent email as following.

Drywall & Trim Stage (Approximately 30 Business Days)*supply propane for temp heat if necessary*

  • Drywall hung, taped and finished
  • Interior Trim, Paint Interior
  • Flooring
  • Kitchen Cabinets 37 calendar days to the ProHome Orientation walk (if all utilities completed)
  • Countertops and Vanities
  • CABINET WALK

 

Final Stage (Approximately 30 Business Days)

  • HVAC, Electrical, & Plumbing Fixtures
  • Appliances Installed
  • Complete Painting & Touch-up
  • Carpet
  • Cleaning
  • Final Grade (35’ around house)

PRO-HOME ORIENTATION WALK 5 business days to your NDI settlement

 

NDI Settlement Must have Occupancy permit at least 24 hours prior to settlement

Push Dominion power for the new pole

There are still no sign of the new pole for electricity.

Jin sent a very nice email to push Mr. Garza,  the Dominion representative responsible for our work request, and he replied immediately.

His email said although our project was set up to work on 12/22/15, he will try his best to move it as early as possible.  If the weather is perfect, they might be able to install the pole next week.

Met Vince and estimate move in date as 1/15/16

When I was checking our new house this morning, I happened to meet Vince, our new project manager.  He was very nice and showed me the schedule for our house and gave us an informal move in date.  He estimated it as 1/15/2016.  However, there are a lot of uncertainty elements like electricity, weather, etc.  Anyway, it is a good news for us.  Thank you Vince!

IMG_3538[1]